Every month
Sealed Schedule Record
I seal each update on receipt, and my engine recomputes each facility’s path from the sealed file.
Read more about the Sealed Schedule RecordI review your P6 baseline at a fixed price, seal it as month zero, then seal each update so every facility’s driving path can be re-checked from the file. Done by the senior practitioner named below. Turnaround agreed in writing at booking.
Why the baseline matters
The accepted baseline’s logic, durations, constraints, calendars and facility driving paths become the reference for windows analysis, as-planned versus as-built comparisons and impacted analyses. A defect accepted on day one carries through every one of them.
Who it is for
Know which work drives each facility’s finish before you accept the baseline.
Submit a baseline whose logic carries your entitlement later.
Your planners cannot mark their own homework in front of a board, lender or client. I do that work, from outside the project team.
The flagship
A review of the baseline before it is accepted or submitted, read for what a later delay analysis would rest on.
On time and complete, or I complete it at no charge and credit part of the fee. It covers the work, not the finish date or any claim.
Book a Baseline Review scoping callFactual; not an expert-witness opinion unless separately agreed.
Not ready? The Baseline Red-Flag Scan, under NDA, gives up to ten red flags, ranked. Its fee is credited to a Review booked within the agreed window.
The record, in brief
| Entry | Data date | SHA-256 of .xer | Facility B finish | Driving path note |
|---|---|---|---|---|
| Update 09 | 31 Oct 2027 | 5a08…d7e2 | 21 Dec 2028 | Facility B path changedPATH CHANGE from gas turbine generator work to substation 2 cabling. |
After the baseline
Every month
I seal each update on receipt, and my engine recomputes each facility’s path from the sealed file.
Read more about the Sealed Schedule RecordAt decision gates
I run the analysis: P50 and P90 per facility, with inputs recorded so the run can be repeated.
Read more about Reproducible Risk AnalysisIf a dispute comes
I hand over the sealed record as a factual base. Not an expert-witness opinion unless separately agreed.
Read more about Delay Support from the RecordTell me about the project, the baseline and when it is due to be submitted or accepted.
I reply within two working days. How I handle your files.